Construction Update for 3.3.14

SHC Construction Update, 3.3.14 Future Stanford Hospital & Parking Structure; Garden Entrance/Tunnel Construction; Ramp Construction Work; Steam Plant Construction New Viewing Platform of Construction Site A new viewing platform has been constructed for patients, visitors and staff to come take a look at the construction...

Read More

Construction Update for 2.24.14

Ramp Construction Work Saw-cutting work was successfully completed over the weekend. Non saw-cutting activities will continue during regular construction hours (7am-3pm) in the main corridor on the ground level of the Main Hospital. Wooden barricades are up and alternative routes have been identified in...

Read More

Construction Update for 2.17.14

Future Stanford Hospital & Parking Structure Regular work hours are 7 am-6 pm M-F on the Future Stanford Hospital site; 9 am-6 pm on Saturdays; no night work scheduled for next week. *The site will remain open with limited work occurring on Presidents Day, Monday,...

Read More

Construction Update for 2.10.14

Please note: work is subject to change due to weather. Future Stanford Hospital & Parking Structure Regular work hours are 7 am-6 pm M-F on the hospital site; 9 am-6 pm on Saturdays; a concrete pour may occur next Tuesday, 2/11, between 6 am and...

Read More

Construction Update for 2.3.14

Future Stanford Hospital & Parking StructureRegular work hours are 7 am-6 pm M-F; 9 am-6 pm on Saturdays; no night work scheduled.This Week (2/3-2/7):Hospital Site:Hospital foundation pile installation, waterproofing, forming work, rebar and placement preparations for the foundation continue. The next concrete pour for the hospital...

Read More

Construction Update for 1.27.14

Future Stanford Hospital & Parking StructureRegular Work Hours: 7 am-6 pm M-F; 9 am-6 pm on Saturdays; no night work scheduled for next week.This Week (1/27-1/31):Hospital Site:Hospital foundation pile installation continues through the end of January Waterproofing, forming work, rebar and placement preparations for the foundation...

Read More

First Concrete Pour Lays Foundation for Future Stanford Hospital

Dozens of trucks loaded with concrete lined up this week to kick off an important milestone in construction of the Future Stanford Hospital: the very first concrete pour to create the new building’s foundation.With mass excavation of the construction site complete, crews began the first...

Read More

Demolition Resumes in Garden Entrance

Demolition of the former MRI offices has resumed in the Garden Entrance of Stanford Hospital. The work will allow crews to make way for a tunnel that will connect the current hospital building to the future hospital building. Demolition will be complete at the end...

Read More

Construction Update for 1.20.14

Future Stanford Hospital & Parking StructureRegular work hours are 7 am-6 pm M-F on the Future Stanford Hospital site; 9 am-6 pm on Saturdays; no night work scheduled for this week.This Week (1/20-1/24):Hospital foundation pile installation will continue An all-day concrete pour is scheduled to occur...

Read More

Construction Update for 1.13.14

Steam Plant Effective Monday, January 13, 2014 at 7 a.m., parking lot L-9 (Lot 9), also known as the J-Lot, located on Quarry Extension near the entrance to the Emergency Department will close permanently. The parking lot is closing in order to accommodate...

Read More