Construction Update for 5.5.15

SHC Construction Update, 5.5.14 Ramp Construction Work General ramp construction activities continue in the main corridor on the ground level of Stanford Hospital during regular construction hours (7am-3pm) This work is not anticipated to cause noise or disruption inside of the hospital Hallway...

Read More

Construction Update for 4.28.14

SHC Construction Update, 4.28.14Ramp Construction WorkGeneral construction activities will continue during regular construction hours (7am-3pm) in the main corridor on the ground level of Stanford Hospital This work is not anticipated to cause noise or disruption inside of the hospital Hallway barricades are up and alternative...

Read More

Construction Update for 4.21.14

SHC Construction Update, 4.21.14Ramp Construction WorkGeneral construction activities will continue during regular construction hours (7am-3pm) in the main corridor on the ground level of the Main Hospital and are not anticipated to cause noise or disruption inside of the hospital Please note, hallway barricades are...

Read More

Oak Road Closure and Marguerite Changes, Beginning 4.15.14

Oak_Rd_Closure_Flyer Beginning Tuesday, April 15th, Oak Road will close to through traffic in order to accommodate ongoing Stanford University SESI utility work. Access to the Stock Farm garage (Parking Structure 5) and parking lots will be maintained via Stock Farm between Oak and Welch Roads....

Read More

Construction Update for 4.14.14

SHC Construction Update, 4.14.14Ramp Construction WorkGeneral construction activities will continue during regular construction hours (7am-3pm) in the main corridor on the ground level of the Main Hospital and are not anticipated to cause noise or disruption inside of the hospital Please note, hallway barricades are...

Read More

Construction Update for 4.7.14

Ramp Construction Work General construction activities will continue during regular construction hours (7am-3pm) in the main corridor on the ground level of the Main Hospital Hallway barricades are up and alternative routes have been identified in the affected corridors for patients and staff ...

Read More

Construction Update for 3.31.14

SHC Construction Update, 3.31.14Ramp Construction WorkChipping work on the footings is scheduled for next Sunday, 4/6 from 9am to 7 pm. This work is anticipated to cause some noise and vibration inside of the hospital, especially in Endoscopy, MRI, the Cafeteria and adjacent corridor,...

Read More

Construction Update for 3.24.14

SHC Construction Update, 3.24.14Ramp Construction WorkActivities will continue during regular construction hours (7am-3pm) in the main corridor on the ground level of the Main Hospital Hallway barricades are up and alternative routes have been identified in the affected corridors for patients and staffFor more information...

Read More

Construction Update for 3.17.14

SHC Construction Update, 3.17.14 New Viewing Platform of Construction Site A new viewing platform has been constructed for patients, visitors and staff to observe the construction action over the fence at the future Stanford Hospital (500 Pasteur Drive). It is located outside the Pasteur...

Read More

Construction Update for 3.10.14

SHC Construction Update, 3.10.14 Future Stanford Hospital & Parking Structure; Garden Entrance/Tunnel Construction; Ramp Construction Work; Steam Plant ConstructionNew Viewing Platform of Construction SiteA new viewing platform has been constructed for patients, visitors and staff to observe the construction action over the fence at the future...

Read More