Construction Update 7.21.14

SHC Construction Update, 7.21.14Stanford Hospital & Parking Structure ConstructionRegular work hours are 6am-8pm M-F on the Stanford Hospital site; 7am-6pm on Saturdays; no night work scheduled for next week.This Week (7/21-7/25):Hospital Site:Foundation pours and off-haul will continue Structural steel assembly began Monday, 6/30 Work to...

Read More

Construction Update 7.14.14

Future Stanford Hospital & Parking Structure Regular work hours are 6am-8pm M-F on the Future Stanford Hospital site; 7am-6pm on Saturdays; no night work scheduled for next week. This Week (7/14-7/18): Hospital Site: Foundation pours and off-haul will continue for the...

Read More

Construction Update 7.7.14

SHC Construction Update, 7.7.14 Future Stanford Hospital & Parking Structure Regular work hours are 6am-8pm M-F on the Future Stanford Hospital site; 7am-6pm on Saturdays; no night work scheduled for next week. This Week (7/7-7/11): Hospital Site: General construction activities...

Read More

Construction Update 6.30.14

SHC Construction Update, 6.30.14Future Stanford Hospital & Parking StructureRegular work hours are 6am-8pm M-F on the Future Stanford Hospital site; 7am-6pm on Saturdays; no night work scheduled for next week.This Week (6/30-7/4):Hospital Site:General construction activities will continue to progress work on the...

Read More

Construction Update for 6.23.14

Future Stanford Hospital & Parking StructureRegular work hours are 6am-8pm M-F on the Future Stanford Hospital site; 7am-6pm on Saturdays; no night work scheduled for next week.This Week (6/23-6/27):Hospital Site:General construction activities will continue to progress work on the building’s foundation as well as...

Read More

Construction Update for 6.16.14

Future Stanford Hospital & Parking StructureRegular work hours are 6am-8pm M-F on the Future Stanford Hospital site; 7am-6pm on Saturdays; no night work scheduled for next week.This Week (6/16-6/20):Hospital Site:General construction activities will continue to progress work on the building’s foundation as well as...

Read More

Construction Update for 6.9.14

SHC Construction Update, 6.9.14Future Stanford Hospital & Parking StructureRegular work hours are 6am-8pm M-F on the Future Stanford Hospital site; 7am-6pm on Saturdays; no night work scheduled for next week.This Week (6/9-6/13):Hospital Site:General construction activities will continue to construct the building’s foundation...

Read More

Stanford Hospital Team Installs Base Isolators

By Jessie FetterlingPALO ALTO, Calif. — Construction of the new 824,000-square-foot, 600-bed Stanford Hospital on the Stanford University Medical Center (SUMC) campus in Palo Alto is well underway. While the new facility will enhance capacity, it will also accommodate new medical technology as well as...

Read More

Construction Update for 6.2.14

SHC Construction Update, 6.2.14 Future Stanford Hospital & Parking Structure Regular work hours are 6am-8pm M-F on the Future Stanford Hospital site; 7am-6pm on Saturdays; no night work scheduled for next week. This Week (6/2-6/6): Hospital Site: General construction activities...

Read More

Construction Update for 5.26.14

SHC Construction Update, 5.26.14Future Stanford Hospital & Parking StructureRegular work hours are 6am-8pm M-F on the Future Stanford Hospital site; 7am-6pm on Saturdays; no night work scheduled for next week.This Week (5/26-5/30):Hospital Site:General construction activities will continue to construct the building’s foundation...

Read More