Construction Update 10.6.14

SHC Construction Update, 10.6.14 NOTICE: Edwards Building (SoM): Electric tools will be used, causing loud noise and frequent vibration between 10 p.m. - 6 a.m. on the North side of the building. Pneumatic Tube Upgrade Project (P-Tube): Project work in the Atrium is scheduled...

Read More

Construction Update 9.29.14

SHC Construction Update, 9.29.14Stanford Hospital & Parking Structure ConstructionRegular work hours are 6 a.m. – 8 p.m., M-F; 7 a.m. – 6 p.m. on Saturdays; no night work scheduled for this week.This Week (9/29-10/3):Hospital Site:Waterproofing, forming work, rebar, grade beam placement and preparations...

Read More
image title

Ground Floor Construction

Remember the first time you went to a show and saw your favorite band. You wore their shirt, and sang every word. You didn't know anything about scene, haircuts, or what was cool. All you knew was that this music made you feel different from...

Read More

Construction Update 9.15.14

SHC Construction Update, 9.15.14Stanford Hospital & Parking Structure ConstructionRegular work hours are 6 a.m. – 8 p.m., M-F; 7 a.m. – 6 p.m. on Saturdays; no night work scheduled for this week.This Week (9/15-9/19):Hospital Site:Waterproofing, forming work, rebar, grade beam placement and preparations...

Read More

Construction Update 9.8.14

SHC Construction Update, 9.8.14 Stanford Hospital & Parking Structure Construction Regular work hours are 6 a.m. – 8 p.m., M-F; 7 a.m. – 6 p.m. on Saturdays; no night work scheduled for this week. This Week (9/8-9/12): Hospital Site: Waterproofing, forming...

Read More

Construction Update 8.25.14

SHC Construction Update, 8.25.14 Stanford Hospital & Parking Structure Construction Regular work hours are 6 a.m. – 8 p.m., M-F; 7 a.m. – 6 p.m. on Saturdays; no night work scheduled for this week. This Week (8/25-8/29): Hospital Site: Waterproofing, forming...

Read More

Construction Update 8.18.14

SHC Construction Update, 8.18.14 Stanford Hospital & Parking Structure Construction Regular work hours are 6 a.m. – 8 p.m., M-F; 7 a.m. – 6 p.m. on Saturdays; no night work scheduled for this week. This Week (8/18-8/22): Hospital Site: Waterproofing, forming...

Read More

Construction Update 8.11.14

SHC Construction Update, 8.11.14Stanford Hospital & Parking Structure ConstructionRegular work hours are 6 a.m. – 8 p.m. M-F on the Stanford Hospital site; 7 a.m. – 6 p.m. on Saturdays; no night work scheduled for this week.This Week (8/11-8/15):Hospital Site:Waterproofing, forming work, rebar,...

Read More

Construction Update 8.4.14

SHC Construction Update, 8.4.14Stanford Hospital & Parking Structure ConstructionRegular work hours are 6am-8pm M-F on the Stanford Hospital site; 7am-6pm on Saturdays; no night work scheduled for this week.This Week (8/4-8/8):Hospital Site:Waterproofing, forming work, grade beam placement and preparations for the foundation will...

Read More

Construction Update 7.28.14

SHC Construction Update, 7.28.14 Stanford Hospital & Parking Structure Construction Regular work hours are 6am-8pm M-F on the Stanford Hospital site; 7am-6pm on Saturdays; no night work scheduled for this week. This Week (7/28-8/1): Hospital Site: Waterproofing, forming work, rebar, grade...

Read More