Construction Update 8.10.15

SHC Construction Update, 8.10.15

 

500 Pasteur Drive Construction

500 Pasteur Drive Construction

  • Project Description: Stanford Health Care is building a hospital facility at 500 Pasteur Drive. The project includes the construction of a seven-story hospital building and four-story parking structure. Construction is scheduled to be completed in 2017 and open to patient care in 2018.
  • Construction Update:
    • Construction crews are completing the steel phase of work including, welding, decking and interior framing of the hospital.
    • Construction crews are installing metal panels and framing the exterior and interior of the parking garage.
  • Construction Hours: Regular work hours are 6 a.m. – 8 p.m., M-F; 7 a.m. – 6 p.m., Sat.

Garden Entrance/Tunnel Construction

  • Project Description: 500 Pasteur Drive will connect seamlessly to the existing hospital building at 300 Pasteur Drive through a pedestrian bridge and walkway as well as a tunnel for supply chain flow, deliveries and waste management transportation. Work will be complete in 2017.
  • Construction Update: Crews are installing rebar and formwork (temporary molds) to prepare for the installation the base isolators for the bridge.
  • Construction Hours: Regular work hours are 6 a.m. – 8 p.m., M-F; 7 a.m. – 6 p.m., Sat.

 

Stanford Hospital Renovations & Upgrades

Waste Management Project

  • Project Description: Work is occurring on the Ground Level of 300 Pasteur Drive to renovate and reconfigure the waste management area to accommodate all future deliveries and shipments for 300 and 500 Pasteur Drive, as well as Lucile Packard Children’s Hospital Stanford. Work will be complete in June 2016.
  • Construction Update:
    • Safety fencing is in place near the Emergency Department parking lot. One lane remains open for emergency vehicles and visitors to access the Emergency Department.
    • Formwork and rebar work is ongoing near the Emergency Department ambulance entrance as part of the waste dock expansion.
    • Occasional night and weekend work may occur with advance notice.
  • Construction Hours: Regular work hours are 7 a.m. – 3:30 p.m., M-F.

Supply Chain Project

  • Project Description: Work is occurring on the Ground Level of 300 Pasteur Drive to renovate and enhance the hospital’s supply chain area to accommodate all future materials and deliveries for 300 and 500 Pasteur Drive, as well as Lucile Packard Children’s Hospital Stanford. Work will be complete in May 2017.
  • Construction Update:
    • Some construction-related noise can be expected during construction hours.
    • Mechanical, electrical and plumbing installation work is ongoing in the ceilings.
  • Construction Hours: Regular work hours are 7 a.m. – 3:30 p.m., M-F.

Spring Refresh Project

  • Project Description: The Spring Refresh C-I-CARE project will replace flooring and baseboards in all major corridors in the B/C Patient Unit (Levels 1, 2 and 3), the Cafeteria and Emergency Department Entrance as well as deep clean patient units, rooms and public spaces while also de-cluttering patient units. Work began in May and will continue through August.
  • Construction Updates:
    • Work is underway to replace the flooring and baseboards in the SHC Cafeteria dining area and the Level 3 corridor. Work will occur in phases to minimize impacts and alternative routes will be identified as needed. Food service will not be interrupted during work hours.
  • Construction Hours: Regular work hours are 4 p.m. – 12 a.m., M-F.

Surgical Pathology Project

  • Project Description: Renovations to modernize and enhance the Surgical Pathology Suite are underway on Level 2 of 300 Pasteur Drive. Work began on Monday, 7/27 and continue through October 2016.
  • Construction Updates:
    • Noise from demolition is expected for about two weeks.
    • Scaffolding will go up in the Central Core courtyard beginning Monday, 8/10.
    • An exhaust fan shutdown will impact surgical pathology on Tuesday, 8/12. The shutdown will occur at night to minimize issues with the users.
    • A crane pick at the fountain entrance is scheduled for Sunday, 8/16.
  • Construction Hours: Regular work hours are 7 a.m. – 4 p.m., M-F. Occasional night and weekend work may occur with advance notice.

Bone Marrow Transplant Project

  • Project Description: The existing hospital facilities are undergoing renovations to modernize and enhance the functional capacity of the Bone Marrow Transplant Laboratory. Work is underway on Level 1 of 300 Pasteur Drive to renovate and reconfigure the Bone Marrow Transplant Laboratory. Work began Monday, 7/27 and continue through September 2016.
  • Construction Updates:
    • Departments will be notified of any impacts to operations on a weekly basis.
    • A Lab Air and Lab Vac shutdown in the BMT lab is anticipated on Wednesday, 8/12.
  • Construction Hours: Regular work hours are 7 a.m. – 4 p.m., M-F. Occasional night and weekend work may occur with advance notice.

 

 

Packard Expansion

Quarry Road Crosswalk—Packard Expansion

The crosswalk on Quarry Road and Quarry Extension (near the construction trailers) will remain closed in order to accommodate deliveries and concrete pours near the perimeter of the construction site. A pedestrian detour is in place.

 

Stanford Neuroscience Health Center

Stanford Neuroscience Health Center

  • Project Description: Construction of the five-story, 92,000-square-foot Stanford Neuroscience Health Center is currently underway and scheduled to open this winter. The building will support the growing need for specialized outpatient neurological care, allow for advancements in neurological research and deliver innovative treatments to the community.
  • Construction Update:
    • Crews continue to install the exterior and interior finishes of the building.
    • A rain water retention system is being installed as part of the landscaping.
  • Construction Hours: Regular work hours are 8 a.m. – 4 p.m., M-Sa.